Nripendra Mishra, Chairman of Ram Mandir Building Construction Committee
– Photo : Samvad
Expansion
Tuesday is the second day of the meeting of the Ram Temple Building Construction Committee in Ayodhya, UP. There is still a shortage of workers in construction work. L&T has been asked to increase the number of workers. At the same time, the challenge of making the parikrama route of the parkota i.e. Ram temple still remains. The completed works will be handed over to the Trust within 15 days. Arrangements for botanical beautification are also being made on 20 acres of land in the Ram Mandir complex.