Five Projects Will Ease The Way For Delhiites From 2025 – Amar Ujala Hindi News Live

Five Projects Will Ease The Way For Delhiites From 2025 – Amar Ujala Hindi News Live


Five projects will ease the way for Delhiites by 2025. NCR vehicles will also ply on these routes. Barapula Phase-3 will make the route up to INA signal free for the passengers of East Delhi as well as Noida and Ghaziabad. The movement of Mumbai Expressway through Delhi-Mumbai Access Control Link will be uninterrupted.

From Gagan Cinema flyover located in Nand Nagri, it will be possible to reach Signature Bridge and Ring Road from Trans Hindon including East Delhi. Delhi’s Third Ring Road i.e. Urban Extension Road (UER)-2 will improve the traffic of the border cities of Haryana including outer, western and south-western Delhi. Local withdrawal from Sultanpuri RUB will be fine. All five projects will be completed in 2025.

Movement from Yamuna crossing to South Delhi will be easy

The work of Barapula Phase-3 started in the year 2014 to ease the movement from Yamuna crossing to South Delhi. It was to be completed by 2017. But this plan has not been completed yet. According to the last deadline, it was to be completed by March 2023, but the work could not be completed. Currently 270 trees remain a hindrance in the project. More than 70 percent of its work has been completed. It is targeted to complete it next year.

With the completion of Barapula Phase-3, the journey from Mayur Vihar across Yamuna to INA via Jawaharlal Nehru will be signal free. Commuters of Noida and Ghaziabad will also benefit from this.

Mumbai expressway From will connect dnd

This 59 kilometer long expressway is starting from DND flyover and connecting to KMP Express at Sohna via Kalindi Kunj, Faridabad. Here it is connecting with Delhi-Mumbai Expressway. It is being constructed in three phases. The 26 km stretch from Sector-65 to Sohna in Faridabad has been opened for passengers only last year. Now the 24 km stretch from Sector-65 to Mithapur in Delhi has also been opened for traffic. The nine km stretch from DND to Mithapur is currently being constructed. It will be completed before June next year. This will ease traffic movement in South Delhi.

sky Cinema of will break Jam of tightness

The construction work of the flyover being built between Nand Nagri and Gagan Cinema in North-East Delhi will be completed next year. This road connects Delhi to Ghaziabad. This area of ​​Delhi is densely populated. Its construction work has been 95 percent completed. Many trees have become a hindrance in the project.

Its construction work will start after getting permission to remove trees. In such a situation, its construction work will be completed only after the assembly elections next year. The construction of this flyover from Nand Nagri to Gagan Cinema on Mangal Pandey Marg will benefit Ghonda, Mustafabad, Gokalpur, Nand Nagri, Karawal Nagar and dozens of nearby densely populated colonies. Traffic coming from Ghaziabad (Bhopura Border) of UP and going towards Signature Bridge will have easy movement.

via uer,2 Alipore From airport sprint will fill Vehicle

The journey from Alipur in the capital to the airport via Najafgarh will be completed in 20 minutes next year. The construction work of UER-2 is in the final stage. The construction work of this 75 kilometer long road is being done in five packages. In this, the construction work of four packages has been completed by more than 90 percent, while the construction work of one package is going on at a slow pace.

sultapuri ROB From Will work traffic

To get rid of the jam, the construction work of the Railway Overbridge (ROB) being built on Sultanpuri-Nangloi Road will be completed next year. Once it is ready, it will not only be easier for the drivers of cars and big vehicles to travel between Sultanpuri and Nangloi, but also for the people of Sultanpuri, Nangloi, Kirari, Poothkalan, Rohini Sector-20, 21, 22, Mangolpuri and many other areas. It will be easy to reach Rohtak Road.